Indescon Court heads to floor 12!

0 Comment

The twelfth floor bridge section of Indescon Court Phase 2 pre-assembled in our Bay 3 assembly shop prior to surface preparation provided an ideal opportunity for a number of our production staff to assemble for a team photograph. Plate girders up to 1500mm deep and 20t in weight form this 90t grillage due to be installed later this year at a level of approximately 43 metres. The twelfth floor structure represents a key milestone in this prestigious project linking adjacent blocks prior to build continuation to floor 19 where the building footprint will increase by means of a 6mtr projection before heading upwards towards floor 32.